Anyone wishing to build or undertake restoration of an existing building or make changes, must obtain a building permit.
What are the necessary parts to building a case for a building permit? A request on plain paper indicating the quality of the petitioner, the location and land area, the nature of work and the destination of buildings. The plan of the land title or, if the land is not registered, a plan booklet prepared by a licensed surveyor. In the case of an uneven ground, a plane including the side contours. Location map extracted from a topographic map or, failing that, a map section containing all indications specific to the location of land. The ground plane in 1/500 scale or on a larger scale with the following information: – The limits of orientation.- terrain.- The implementation of the planned construction and existing buildings to maintain or démolir.- Insurance of neighboring buildings and their approximate height. The plans, sections and facades to scale 1/100 or at a higher level. The plans must be legibly sides, so as to permit assessment of volumes, surfaces and openings, scale must be shown in legend.
They must specify in particular the method of sewage disposal.
They must also bear indications of smoke and ventilation ducts.
They should also give any indication of materials and colors for judging the external appearance of the proposed building.
The destination must be on different local plans. A single copy of statement of income. A Discharge Municipal. Validity of the building permit, its extension and renewal
The building permit is valid for a period of three years from its issue. This validity shall be extended for the same period on request, and when the construction project has not been modified. Applications must reach the technical service of the City Council one month before the expiry of the validity period of the order of building permits whose extension is required.
The building permit is renewed in the same form and conditions for obtaining, in case the construction project has undergone changes.
Response times to requests for permission to build
A decision on the request of building permits within a period not exceeding forty five (45) days from the filing date, on the basis of a duly constituted folder. This period is extended to: Sixty (60) days, if the development plan is being developed. Ninety (90) days if the proposed construction is within the limit of two hundred (200) meters tower – naturels.- sites of cultural and archéologiques.- areas sauvegarde.- historical monuments.